We ended week 7 yesterday! I cannot believe it has been 7 weeks already. In some ways those weeks have flown by but in other ways it feels like we have been building this house FOREVER and it's never getting done! I am assuming that this feeling will continue especially as the house gets closer to being done!
So here is where we started week 7
|
The front of the house |
|
The back of the house |
|
The family room |
And here is how we are ending week 7
|
House painted |
The outside of the house has been painted and the front yard is now ready for sidewalks and our driveway.
|
Back of the house painted |
|
|
|
The family room |
The family room painted along with all our doors and trim painted. The door on the left is for the air handler closet and the door on the right is for the coat closet. Not sure why those were not installed but they were painted.
I think they are going to be installing tile this week, and maybe cabinets, also I think they are going to start the sidewalks and the driveway. Week 8 should be a great week!
39 days to go (if we stay on schedule)
No comments: